Road and street works will commence on Monday 19th June 2017.

We shall be completing the necessary works in Four Phases over an estimated duration of 3 Weeks:
– Phase 1: Church Avenue – St Lawrence O’Toole Ave
– Phase 2: St Lawrence O’Toole Ave – Strand Road
– Phase 3: Strand Road
– Phase 4: Strand Road

The road works and street works are necessary in order to reinstate the new footpaths, landscaped areas, trees and street lighting around the site boundary. Mc Callion Group will aim to carry out these works with as little hindrance as possible to the neighbouring residents and business but we would appreciate the cooperation which has kindly been provided by all since commencing this project.