We are approaching the half way mark of the construction period of the store and the project is on schedule.
– Block Work and associated works are underway.
– Arrival of Glulam beams is scheduled for Friday 14th April. This will be transported to site using methods of assisted special transport.
– Roofing shall commence at the beginning of May.